Jackson East Taylor Sewer Authority, Cambria County
Wastewater Extension: This project involved construction of approximately 19,500 LF of 8” and 6” PVC wastewater main and 2,716 LF of 4” PVC force main, manholes, related appurtenances, and restoration.
The Pump Station project included the construction of two new pump stations, reconstruction of the existing Pump Station #12, and replacement of pumps at the existing Pump Stations #3 and #7, along with related appurtenances and restoration. The information will be entered into the Authority’s existing GIS system.
Municipal Building: This project included demolition of the existing office, utility relocation, a new 1,400 SF office building, design of an ADA concrete sidewalk and parking lot, new signage and two defined entrance/exit locations onto the state road.
Keller Engineers has been an extremely valuable asset for us in the development/construction of our store sites by providing accurate and timely structural and site development drawings and answers to related questions. Their response and turn-around time to the Sheetz Store Development Department has been outstanding. We have no hesitation in turning to Keller Engineers for our store structural and site development needs. Joe S. Sheetz, Executive Vice President, Finance & Store Development Sheetz Corporation