Gardner Denver Company – New Manufacturing Facility

Responsibilities

  • Survey
  • Site Planning, Design, and Layout
  • Parking Lot Design
  • Permitting
  • Stormwater Management
  • Erosion Control
  • Landscape Plan
  • Lighting Plan
  • Utility Design
  • Land Development Approvals
  • Construction Documents
  • Lot Merge Plan

Owner

Original Owner: Gardner Denver Company | Purchased by DelGrosso Foods in 2021

Project Details

This project included the design of a 70,400 SF manufacturing and office space, parking for 110 cars, truck docks, and a maneuver area. The design allows for future expansion.

Project Uniqueness/Challenges:

  • Numerous grading options for balance earthwork
  • Incredibly aggressive schedule to meet contracted building occupancy date
  • Numerous wetland pockets at perimeter of site
  • Coordination with electric company for off-site extension due to high electric demand in facility

Photos

I probably don’t say this enough, but we so appreciate the quality of work Keller Engineers does. The fact that they include building footprints and natural features makes these surveys super useful. I’m reminding my colleagues in other counties that their surveyors need to up their quality. F. Mark Schiavone, Executive Director Berkeley County Farmland Protection Board